### MED - MVC

| Process | Mechanical Vapour Compression |
|---|---|
| Country | Indonesia |
| Contract Description | Design / Supply / Deliver FOB / Supervision of erection / Commissioning of two skid mounted desalination units |
| Contract Date | 2017 |
| Capacity | 2 x 672 m3 product water per day |



### Project Description :

The units will supply distillate process water for the Tangguh LNG plant in Indonesia

### Technical Description :

The plant consists in two Multiple Effect Distillation fitted with a Mechanical Vapour Compressor, 2 x MVC 1 672 units.



 

 

 



 

 